We handle the structural/mechanical scope of transmission line construction — transporting and erecting steel tower structures and completing all welding works before the electrical division carries out stringing.
Key Capabilities
- Transportation of tower material from warehouse to site
- Erection of D/C steel tower structures (ZM1, ZM1+3, and other WAPDA-standard types)
- Installation of ACD (Anti-Climbing Devices), sign plates, and barbed wire
- Electric welding of nuts & bolts on erected towers
- Mobilization/demobilization of labor crew and T&P (tools & plant) at site
Representative Work
- Tower erection — 132kV D/C Liberty-Daharki-TPS Guddu Transmission Line (GSC SEPCO)
- Erection of ZM1 & ZM1+3 type towers — Locations 13 & 14, New Rohri-Nara-I & Solar Power Plant Line
- Welding of 450 nut/bolt sets on Tower Types ZM1 & ZM1+3
PEC Specialization: BC01, ME07(v)